The workload being modeled
This example represents a shop with many 1–8 piece orders rather than long repeat runs. It is where “total head count” can be a misleading purchasing metric.
| Target | 160 good pieces in the modeled window |
|---|---|
| Design | 7,000 stitches per piece |
| Order mix | 20% caps |
| Average same-design batch | 5 pieces |
| Production window | 5 days × 7 hours/day |
| Model allowance | 3% rejects/rework; one operator |
What the same workload looks like on different architectures
The numbers below use the same assumptions as the main planner: 1.45 minutes per 1,000 stitches for flat goods, 2.10 for caps, 1.4 minutes handling for flats, 2.8 for caps and one operator. They are planning examples—not manufacturer ratings.
| Setup | Modeled rate | Good pieces/window | Head utilization | First bottleneck |
|---|---|---|---|---|
| 1 single-head | 5.4/hr | 184 | 100% | Machine |
| 2 independent single-heads | 10.8/hr | 368 | 100% | Machine |
| 2-head synchronized | 9.0/hr | 307 | 83% | Machine |
| 4-head synchronized | 13.6/hr | 460 | 62% | Machine |
| 6-head synchronized | 27.1/hr | 921 | 83% | Machine |
The decision this scenario is actually testing
Independent machines can split different customer jobs while a synchronized bar normally wants identical work across its heads. That flexibility has economic value even when the synchronized machine wins on floor space or operator simplicity for large runs.
Before using this to buy equipment
- Time several real jobs and replace the minutes-per-1,000-stitches assumption.
- Measure hooping/loading time separately from sewing time.
- Use the actual same-design batch size, not invoice quantity.
- Add downtime, maintenance and staffing constraints that matter in your shop.
- Run the shortest real customer deadline, not only the average week.
Questions this example should answer
Does this mean multi-head machines are bad for small shops?
No. It means batch structure matters. A shop with frequent 48- or 72-piece repeats can use synchronized heads very differently from a shop dominated by one-off names and tiny logo runs.
How do I estimate my real average batch?
Look at recent jobs and calculate the number of pieces that truly share the same design, thread setup and production sequence—not simply the total pieces on each invoice.
Planning estimate only. The examples on this page are transparent assumptions, not a claim about the sustained output of any specific embroidery machine.